604-575-7069 info@totalbuild.ca

Location of Project: Mission, B.C.
Date: November 2017 – March 2019

MRC Total Build was engaged in November 2017 by BC Hydro to complete repairs to the Stave Falls Blind Slough Dam Spillway Bridge in Mission, BC after the successful completion of the Hayward Lake project earlier that year. The work included waterproofing the bridge deck, crack infill and concrete patch repairs to the bridge deck and concrete beams. The project was completed on time and on budget in February 2018.  MRC Total Build has since been contracted to complete a second phase of the work, which is scheduled to be completed in March 2019.